You are viewing limited content. For full access, please sign in.

Question

Question

"Tab is improperly connected to other objects"

asked on March 17, 2014 Show version history

In the below process when I click the Validate button I receive the following message:

 

"The gateway named "Approved or Denied?" in the "Main Process" tab is improperly connected to other objects. Gateways cannot have multiple incoming and outgoing sequence flows."

 

Should I be setting up this logic in a different way?

0 0

Answer

APPROVED ANSWER SELECTED ANSWER
replied on March 17, 2014

You'll need another gateway where the "Approved or Denied" gateway is. Gateways can merge or split, but cannot do both. So you need a gateway  in front of your approved or denied gateway to merge the approval process flows.