Question

Is there any way to report on a Form's duration while still in-progress?

asked on August 25

In Forms I generally like to create 2 versions of reports for our processes: currently in progress and all. It seems the Duration column doesn't display anything for instances that are still in-progress. Am I missing something? Is there no way to see how long something has been opened besides doing some mental math?

Additionally, the Insights report has the option to remove weekends and holidays from the calculations (and off-hours?). Is there any way to remove these from the Duration calculation in custom report?

0 0

Replies

replied on August 26

The Duration column in the custom report simply calculates the difference between the end date and the start date. For instances in progress, this value is not available. Removing weekends and holidays from the duration calculation is also not supported currently. Sorry for that.

0 0
You are not allowed to follow up in this post.

Sign in to reply to this post.