Is it possible to set the retention period to days rather than months or years?

asked on August 2, 2024

Is it possible to set the retention period to days rather than months or years? I have a client that would like for certain documents to be destroyed after 10 days from being filed into the repository.

0 0

Replies

replied on August 2, 2024 Show version history

The only solution I can come up with is to use the after event (for 1 year) and with immediate destruction.  Then set the event date to current date minus 1 year plus 10 days.