In the Workflow Designer on the Activities tab for a running instance I have been using the Long-Running filter. Sometimes I will catch an activity that is currently running and it will show the duration of the activity, but when I refresh and see the completed activity duration it is lower than what the running activity reported.

While Running

Completed

Why is there such a large discrepancy? I am using Workflow Designer 10.4.2.246.

0 0

Answer

SELECTED ANSWER
replied on August 11, 2022

It's the current time difference while they're waiting to execute in the queue. Once they're done and the database updates you have the actual run time.

0 0

Replies

replied on August 11, 2022

Has anyone else seen this before?