Sub-Process Order

asked on September 6, 2018

Is there any way to change the order that the sub-processes are shown at the bottom of the Process Diagram?  Currently, they are shown in the order you add them to the main process but I would like to show them in the order they are actually called in the main process.  

0 0

Answer

SELECTED ANSWER
replied on September 6, 2018

This is not currently supported in Forms. The sub-process order is determined by the creation time of the sub-process. 

0 0
replied on September 6, 2018

That is what I figured.  Hopefully in the future we will be able to reorder them similar to reordering sheets in an Excel spreadsheet.  Thanks for the info.

0 0

Replies

replied on September 6, 2018

Yes, place your numbers before the word, example: 1 Sub-Process, 2 Sub-Process, 3 Sub-Process. Hope that helps!