You are viewing limited content. For full access, please sign in.

Question

Question

Change priority on forms task after 2 days

asked on July 11, 2018

Hi guys,

 

Looking if it's possible to be able to change the priority on a user task after 2 days. I can see you can add conditions based on variables, just wondering if it's possible to change these to urgent once they hit a certain date. 

Would the best case be to have a hidden field and set that to +2 days from the current date and then mark it that way?

0 0

Replies

replied on July 11, 2018

Hi Alex, 

 

Adding a hidden field and using that in the conditional would work.  Alternately, you could attach a timer event that waits two days before taking an outflow path to a new user task, and setting the conditional on that one to Set Priority To XX, Always.  

1 0
You are not allowed to follow up in this post.